Home / Project Detail
Delivering reliable and professional solutions backed by years of industry experience
RAIPL executed the installation and testing of a 63 mm HDPE underground fuel piping system at Sorout Prime Fuels, Village Banchari, Palwal, Haryana.
The project covered preparation of the underground piping route, sand bedding, pipe laying, installation of fittings through electrofusion welding, and testing of the completed fuel lines. The network was designed to connect the underground petrol and diesel storage tanks with the dispensing units through dedicated product and vapour-recovery routes.
The project involved execution of the underground HDPE fuel piping network from site preparation through final testing.
Major activities included:
The project execution presentation specifically documents initial site preparation, 150 mm sand bedding, pipe laying, electrofusion welding and final pressure testing as key installation stages.
The Joint Measurement Record documents approximately 151.4 metres of 63 mm HDPE pipe, along with 24 tees, 18 couplers, 14 flanges and 14 flange adaptors.